You have not accepted cookies yet

This content is blocked. Please accept marketing cookies. You can do this here.

Expediting EPCMV to Fast Track Facilities

Aug 01, 2024

Matt Bolin

Director of Project Management

With the rise of fast-track treatments and vaccines, we explore how to expedite the engineering, procurement, construction, management, and validation (EPCMV) process for life sciences facilities.


The new meaning of “fast” 

Pandemic-related viruses have caused the life sciences industry to fast-track treatments, including vaccines. This is a noble pursuit, but there’s no point in rushing if it then takes the typical duration to design, construct, commission, qualify, and validate a manufacturing facility. We will have lost the momentum of this valiant effort.

Fortunately, the tremendous ongoing efforts by hundreds of life sciences companies are supported by the architecture, engineering, and construction (A/E/C) industry, which is applying an expedited engineering, procurement, construction management, and validation (EPCMV) approach to help deliver licensed facilities more quickly.


What Arcadis is doing differently to help our clients fast track these critical projects

Our experience of delivering licensed facilities in the United States has led to the following key concepts that pharmaceutical manufacturers will want to consider when working with an experienced EPCMV partner on a project that needs expedited delivery:

 Begin conceptual design early

 Perform steps in parallel to stack the schedule

 Separate process development from identifying and sourcing a facility shell for the process

 Take calculated, educated risks

The tremendous ongoing efforts by hundreds of life sciences companies are supported by the US industry, which is applying an expedited EPCMV approach to help deliver licensed facilities more quickly.


Begin conceptual design early 

Don’t wait until you are in late-stage clinical trials with a molecule to begin facility layouts and process flow diagrams for the manufacturing process. Getting a head start on these conceptual designs will help develop early cost estimates, determine available schedule options and critical path activities, and identify the technology that can be deployed fastest. Beginning conceptual design early involves little risk and can gain weeks or months on your timeline.

  • Read more

Perform steps in parallel and stack your schedule

Some design, construction, and commissioning activities, which are traditionally performed sequentially, can in fact be done in parallel by making educated decisions early. It requires considering how much to vertically stack your schedule that would otherwise be executed linearly. For example, overlapping final detailed design elements with some of the early construction activities (e.g., procurement of long-lead items and construction enabling works) and early CQV (e.g., identifying system boundaries and creating commissioning and validation plans) can gain quite a lot of time. This does require detailed planning and dedicated resources.

  • Read more

Separate design of the process from obtaining a shell that will house it

Another example of how we stack activities to go faster is to build out or source the facility before knowing the final interior process space requirements. First, we work with the client to block out, in general terms, the area they will need for their new process. From there, we can estimate the total facility area requirements to include all ancillary and support spaces. During this blocking process, we also work through plans for growth, expansion, and future buildout.

  • read more

Take calculated, educated risks

These decisions require a willingness to take calculated risks early in the process based on educated assumptions about several factors, including:

Size of the facility

Size of the facility

The need for a nominal square foot building shell may not take planned expansion into account. If the client is bullish about their vaccine, they might decide to shop for a larger space to allow for future growth.

Selection of long-lead equipment (type and size)

Selection of long-lead equipment (type and size)

Early procurement of long-lead equipment aids in removing it from the project’s critical path.

Volume of product and in-process material

Volume of product and in-process material

This will impact process equipment and facility size. (See below.)

Process equipment not final

Process equipment not final

Design to accommodate various processes.

Greenfield, Brownfield, or CMO?

Whether to build a greenfield project, retrofit an existing facility, or outsource to a Contract Manufacturing Organization (CMO) is a question we are often asked. In the instance of an extremely fast-tracked project, a facility location decision can be influenced by staffing and tech transfer. So, retrofitting existing space, if available, is a favourable option.

  • read more

Applying a Lean project delivery model speeds up EPCMV

Lean is the fastest, most effective, and safest way to deliver projects. Projects that have a high-intensity Lean focus are three times more likely to finish ahead of schedule and twice as likely to finish under budget than traditional projects.1 Lean is based on collaboration between engineering design and construction management and reduces the redundancy and waste that occur in traditional executions. We commonly use several Lean principles on project work regardless of whether the project is following this method of delivery.

1 Lean Construction Institute. "Lean Projects Are Three Times More Likely To Complete Ahead Of Schedule According To Dodge Data & Analytics' Research." 22 December 2016.

 

Below are some Lean methods that can expedite project delivery on any project, particularly during a pandemic climate:

  • Pull planning
  • Modular design and execution
  • Integrated project delivery (IPD)
  • Conditions of Satisfaction (CoS)
  • The Big Room
  • Building Information Modelling (BIM) and Virtual Design Construction (VDC)

Procure long-lead equipment during the early/conceptual design phase

Since obtaining specialized process equipment is typically the longest lead item during EPCMV, making educated assumptions about the type, size, and utility requirements of the equipment that needs to be ordered will speed up project delivery.

  • read more

Include Commissioning, Qualification, and Validation (CQV) from the beginning

The endgame of any CQV effort is to deliver a fully validated facility, utilities, HVAC, and process systems, as per GMP requirements. This process can be lengthy and onerous, and a product cannot be manufactured until it is completed.

In an expedited EPCMV project, there are several key elements to ensure the timely and robust delivery of the CQV effort. The most important point is to involve the validation experts as early in the project as possible. This allows them to verify requirements, understand or help develop a CQV strategy and project approach, and establish an on-site presence that will expedite downstream execution efforts.

  • read more

Establishing URSs, conducting risk assessments, and writing the VMP lay the foundation for the project. Now that the validation team is involved, they can get an early start on the development of testing protocols. Having been involved from the start, they will have stronger systems knowledge and be able to generate better protocols, reducing review and approval times.

 A good rapport and familiarity built with the client, the construction team, and vendors:

 Expedites the CQV process

 Allows smoother execution

 Results in fewer discrepancies and retests

 Provides a better understanding of the CQV quality needs, allowing for greater leveraging of vendor test documentation

Involving validation as part of the EPCMV team early and often in the project is the key to success, especially in the case of an expedited project. It allows for greater CQV planning earlier and this results in time-saving activity later in the process.


Trust your EPCMV partner

To abide by quicker timeframes, you should pick a tried and trusted design, construction management, and CQV partner. Here are some things to consider when looking for an EPCMV vendor:

  • Cultural alignment
  • Agile practices
  • Experience working remotely

Expediting a fast-track facility requires working outside of traditional office hours including nights, weekends, and holidays, with a team that trusts each other and believes in the same end-goal (in this case, developing a process to make an effective vaccine as quickly and safely as possible). Without a cohesive team, you risk cost, schedule, quality, and, ultimately, the project.

Connect with {name} for more information & questions

Arcadis will use your name and email address only to respond to your question. More information can be found in our Privacy policy